HMS Construction was subcontracted by Electrical Consultants, Inc. to construct the 46-34.5 kV Substation and 46kV Gen-Tie Line for the Eurus – Waianae Solar Project.
Substation; HMS to supply labor, equipment, and consumable materials as follows; excavation & installation of substation foundations, underground and above grade conduit & grounding system, erect steel, place insulators, panels, equipment, buss, jumpers, and assist with pre-fab control building (installation & various electrical work). HMS also installed & terminated all control cables including assisting with the final commissioning and placement of the finish rock pad around the entire substation.
Gen-Tie Line; Excavation & installation of multi-piece steel poles, frame & set 2- riser poles and 1 tangent pole (OH conductor insulators, conductor attachments, switches and switch operation mechanisms including jumpers to substation. HMS also strings, sag, clip-in & terminates 556.5 kCM ACC wire, and splices the new transmission electrical conductor between structures. Gen-tie line also consists of the installation of 1600LF of underground conduit & manhole system. HMS was contracted to install a 750 kcal (3) phase 46kV underground conductor including installation of riser terminations and splices in a manhole. May 2016 to September 2017.
To provide the best experience, we use technologies like cookies to store and/or access device information. By clicking "Accept All", you consent to our use of cookies to process data for observing site usage and marketing efforts. You can manage your preferences or withdraw your consent at any time by clicking “Preferences”.